Construction Updates

The Union is making progress! Be sure to check out this page for the most up to date pictures on the construction progress being made!

3/27 Construction Updates!


·       Wood framing is 100% complete.
·       Roofing will be 100% by Monday.
·       Air conditioning ductwork, Plumbing piping, electrical wiring, and fire sprinklers approximately 80% completed.
·       Exterior building wrap and window installation 80% completed.
·       Exterior siding has started in the courtyards.
·       Brick façade scheduled to start on Monday, March 30th.
·       Mechanical, Plumbing, and Electric rough-in (behind walls) inspections have started with the interior sheetrock scheduled to start within weeks.


3/27 Drone Footage!